Ministry of External Affairs Government of India

The Government of India and the Government of Pakistan, being equally desirous of attaining the most complete and satisfactory u ilisation of the waters of the Indus system of rivers and recognising the need, therefore, of fixing and delimiting, in a spirit of goodwill and friendship, the rights and obligations of each in relation to the other concerning the use of these waters and of making provision for the settlement, in a cooperative spirit, of all such questions as may hereafter arise in regard to the interpretation or application of the provisions agreed upon herein, have resolved to conclude a Treaty in furtherance of these objectives, and for this purpose have named as their plenipotentiaries :

THE GOVERNMENT OF INDIA:

Shri JAWAHARLAL NEHRU,
Prime Minister of India,

and
THE GOVERNMENT OF PAKISTAN
Field Marshal MOHAMMAD AYUB KHAN, HP., H.J.,
President of Pakistan;

who, having communicated to each other their respective Full Powers and having found them in good and due form, have agreed upon the following Articles and Annexures ;

As used in this Treaty:

but the term does not include Agricultural Use or use for the generation of hydro-electric power.

  1. Any act of withdrawal therefrom; or
  2. Any man-made obstruction to their flow which causes a change in the volume (within the practical range of measurement) of the daily flow of the water : Provided however that an obstruction which involves only an insignificant and incidental change in the volume of the daily now, for example, fluctuations due to afflux caused by bridge piers or a temporary by-pass, etc., shall not be deemed to be an interference with the waters.

Provisions Regarding Eastern Rivers

Provisions Regarding Western Rivers

Provisions Regarding Eastern Rivers and Western Rivers

Period of Aggregate Payment of India
Extension Payment
to of Transition Period
One year stg. 3,125,000
Two years. stg 6,406,250
Three years stg 9,850,000

Exchange of Data

These data shall be transmitted ' monthly by each Party to the other as soon as the data for a calendar month have been collected and tabulated, but not later than three months after the end of the month to which they relate : Provided that such of the data specified above as are considered by either Party to be necessary for operational purposes shall be supplied daily or at less frequent intervals, as may be requested. Should one Party request the supply of any of these-data by telegram, telephone, or wireless, it shall reimburse the other Party for the cost of transmission.

The formal arrangements, in each case, shall be as agreed upon between the Parties.

Permanent Indus Commission

Settlement of Differences and Disputes

Provided that, at the discretion of the Commission, any difference may either be dealt with by a Neutral Expert in accordance with the provisions of Part 2 of Annexure F or be deemed to be a dispute to be settled in accordance with the provisions of Paragraphs (3), (4) and (5), or may be settled in any other way agreed upon by the Commission.

  1. upon agreement between the Parties to do so; or
  2. at the request of either Party, if, after negotiations have begun pursuant to Paragraph (4), in ' its opinion the dispute is not,likely to be resolved by negotiation or mediation; or
  3. at the request of either Party, if, after the expiry of one month following receipt by the other Government of the invitation referred to in Paragraph (4), that Party comes to the conclusion that the other Government is unduly delaying the negotiations.

If, at any time prior to 31st March 1965, Pakistan should represent to the Bank that, because of,the outbreak of large-scale international hostilities arising out of causes beyond the control of Pakistan, it is unable to obtain from abroad the materials and equipment necessary for the completion, by 31st March 1973, of that part of the system of works referred to in Article IVU) which relates to the replacement referred to therein, (hereinafter referred to as the replacement element") and if, after consideration of this representation in consultation with India, the Bank is of the opinion that

the Bank shall immediately notify each of the Parties accordingly. The Parties undertake, without prejudice to the provisions of Article XII (3) and (4), that, on being so notified, they will forthwith consult together and enlist the good offices of the'Bank in their consultation, with a view to reaching mutual agreement as to whether or not, in the light of all the circumstances then prevailing, any modifications of the provisions of this Treaty are appropriate and advisable and, if so, the nature and the extent of the modifications.

Each of the Parties agrees that it will not invoke this Treaty, anything contained therein, or anything arising out of the execution thereof, in support of any of its own rights or claims whatsoever or in disputing any of the rights or claims whatsoever of the other Party, other than those rights or claims which are expressly recognized or waived in this Treaty.

IN WITNESS WHEREOF the respective Plenipotentiaries have signed this Treaty and have hereunto affixed their seals.

DONE in triplicate in English at Karachi on this Nineteenth day of September 1960.

For the Government of India
(Sd) JAWAHARLAL NEHRU
For the Government of Pakistan
(Sd) MOHAMMAD AYUB KHAN
Field Marshal, H.P., H.J.

For the International Bank for Reconstruction and Development for the purposes specified in Articles V and X and Annexures F, G and H:

ANNEXURE A-EXCHANGE OF NOTES BETWEEN GOVERNMENT OF INDIA AND GOVERNMENT OF PAKISTAN

I. Note dated 19th September 1960, from the High Commnissioner for India in Pakistan, Karachi, to the Minister for Foreign Affairs and Commonwealth Relations, Government of Pakistan.

19th September, 1960

I have been instructed by my Government to communicate to you the following :

"The Government of India agrees that, on the ratification of the Indus Waters Treaty 1960, the Inter-Dominion Agreement on the Canal Water Dispute signed at New Delhi on 4th May 1948 (of which a copy is annexed hereto) and the rights and obligations of either party thereto claimed under, or arising out of, that Agreement shall be without effect as from Ist April 1960.

The position of the Government of India stated above and Your Excellency's Note of to-day's date stating the position of the Government of Pakistan on this question will form part of Annexure A to the Indus Waters Treaty 1960."

Accept, Excellency, the renewed assurance of my highest consideration.

SHAUKAT HYAT KHAN

New Delhi, May 4, 1948.

II. Note dated 19th September 1960, from the Minister for Foreign Affairs and Commonwealth Relations, Government of Pakistan, to the High Commissioner for India lit Pakistan, Karachi.

19th September, 1960

I have been instructed by my Government to communicate to you the following :

"The Government of Pakistan agrees that, on the ratification of the Indus Waters Treaty 1960, the document on the Canal Water Dispute signed at New Delhi on 4th May 1948 (of which a copy is annexed hereto) and the rights and obligations of either party thereto claimed under, or arising out of, that document shall be without effect as from 1st April 1960.

The position of the Government of Pakistan stated above and Your Excellency's Note of to-day's date stating the position of the Government of India on this question will form part of Annexure A to the Indus Waters Treaty 1960."

Accept, Excellency, the renewed assurance of my highest consideration.

JAWAHARLAL NEHRU
SWARAN SINGH
N.V. GADGIL

GHULAM MOHD
SHAUKAT HYAT KHAN
MUMTAZ DAULTANA

New Delhi, May 4, 1948.

ANNEXURE B-AGRiCULTURAL USE BY PAKISTAN FROM CERTAIN TRIBUTARIES OF THE RAVI

(i) the area irrigated, and

(ii) the area cultivated on sailab.

ANNEXURE C-AGRICULTURAL USE BY INDIA FROM THE WESTERN Rivers

(Article III (2) (c)

Name of Canal Maximum withdrawals for Agricultural Use
(a) Ranbir Canal 1,000 cusecs from 15th April to 14th October, and
350 cusecs from 15th October to 14th April.
(b) Pratap Canal 400 cusecs from 15th April to 14th October, and
100 cusecs from 15th October to 14th April.
  1. The maximum withdrawals shown above shall be exclusive of any withdrawals which may be made through these canals for purposes of silt extraction on condition that the waters withdrawn for silt extraction are returned to The Chenab.
  2. India may make additional withdrawals through the Ranbir Canal up to 250 cusecs for hydro-electric generation on condition that the waters so withdrawn are returned to The Chenab.
  3. If India should construct a barrage across the Chenab Main below the head regulators of these two canals, the withdrawals to be then made, limited to the amounts specified in (a) and (b) above, during each 10-day period or sub-period thereof, shall be as determined by the Commission in accordance with sound irrigation practice and, in the absence of agreement between the Commissioners, by a Neutral Expert in accordance with the Provisions of Annexure F.
  1. from The Jhelum : 21st June to 20th August
  2. from The Chenab : 21st June to 31st August

Provided that withdrawals for such irrigation, whether from General Storage or from river flow, are controlled by Government.

  1. from The Jhelum 150,000 acres :
  2. from The Chenab 25,000 acres during the Trasition Period and 50,000 acres after the end of the Transition Period. Inaddition to the areas specified in (a) above, there may be developed from The Jhelum or The Chenab an aggregate area 150,000 acres if there is released annually from

Conservation Storage, in accordance with Paragraph 8, a volume of 0.2 MAF into The Jhelum and a volume of 0.1 MAF into The Chenab; provided that India shall have the option to store on and release into The Chenab the whole or a part of the volume of 0.2 MAF s ifi d into The Jhelum.

Any additional areas over and above those specified in (a) above may be developed if there is released annuallyfrom Conservation Storage a volume of 0.2 MAF into in Jhelum or The Chenab, in accordance with Paragrpah 8,addition to the releases specified in (b) above.

  1. As soon as the statistics for each crop year (commencing with the beginning of kharif and ending with the end of the following rabi) have been compiled at the District Headquarters, but not later than the 30th November following the end of that crop year, India shall furnish to Pakistan a statement showing for each of the Districts and Tehsils irrigated from the Western Rivers, the total Irrigated Cropped Areas (excluding the area irrigated under the provisions of Paragraph 3) arranged in accordance with items (a), (b), (c) W and (c) (ii) of Paragraph 5 : Provided that, in the case of areas in the Punjab, the 30th November date specified above may be extended to the following 30th June in the event of failure of communications.
  2. If the limits specified in Paragraph 7(a) or 7(b) are exceeded for any crop year, the statement shall also show the figures for Irrigated Cropped Areas falling under Paragraph 6(a) and 6(b) respectively, unless appropriate releases from Conservation Storage under the provisions of Paragraph 8 have already begun to be made.

ANNEXURE D-GENERATION OF HYDRO-ELECTRIC POWER BY INDIA ON THE WESTERN RIVERS

(Article III (2) d)

The average discharge for each 10-day period (Ist to 10th, I 1th to 20th and 21st to the end of the month) will be worked out for each year for which discharge data, whether observed or estimated, are proposed to be studied for purposes of design. The mean of the yearly values for each 10-day period will then be worked out. The lowest of the mean values thus obtained will be taken as the minimum mean discharge. The studies will be based on data for as long a period as available but may be limited to the latest 5 years in the case of Small Plants (as defined in Paragraph 18) and to the latest 25 years in case of other Plants (as defined in Paragraph 8)."Secondary Power" means the power, other than Firm Power, available only during certain periods of the year.

Part 2-Hydro-Electric Plants in Operation, or under Construction, as on the Effective Date

  1. If any alteration proposed in the design of any of the plants specified in Paragraphs 3 and 4 would result in a materials change in the einformation furnished to Pakistan under the period of three months specified in Paragraph 10 shall be reduced to two months.
  2. If any alteration proposed in the design of a Plant after it comer, into operation would result in a material change in the information furnished to Pakistan under the provisions of Paragraph 9, India shall, at least four months in advance of making the alteration, communicate particulars of the change to Pakistan in writing and the provisions of Paragraphs 10 and 11 shall then apply, but the period of three months specified in Paragraph 10 shall be reduced to two months.
  1. where a Plant is located at a site on the Chenab Main below Ramban, the volume of water received in the river upstream of the Plant in any one period of 24 hours shall be delivered into the river below the Plant within the same period of 24 hours;
  2. where, a plant is located at a site on the Chenab Main above Ramban, the volume of water delivered into the river below the Plant in any one period of 24 hours shall not be less located at the highest level, consistent with sound and economical design and with satisfactory operation of the works.
  3. where, a plant is located at a site on the Chenab Main above Ramban, the volume of water delivered into the river below the Plant in anv one period of 24 hours shall not be less located at the highest level, consistent with sound and economical design and with satisfactory operation of the works.
  4. If the conditions at the site of a Plant make a gated spillway necessary, the bottom level of the gates in normal closed position shall be located at the highest level consistent with sound and economical design and satisfactory construction and operation of the works.
  5. The intakes for the turbines shall be located at the highest level consistent with satisfactory and economical construction and operation of the Plant as a Run-of-River Plant and with customary and accepted practice of design for the designated range of the Plant's operation.
  6. If any Plant is constructed on the Chenab Main at a site below Kotru (Longitude 74' - 59' East and Latitude 33' - OW North), a Regulating Basin shall be incorporated.
  1. If any alteration proposed in the design of a Plant before it comes into operation would result in a material change in the information furnished to Pakistan under the provisions of Paragraph 9, India shall immediately communicate particulars of the change to Pakistan in writing and the provisions of Paragraphs 10 and 11 shall then applv. but theperiod of three months specified in Paragraph 10 shall be reduced to two months.
  2. If any alteration proposed in the design of a Plant after it comes into operation would result in a material change in the information furnished to Pakistan under the provisions of Paragraph 9, India shall, at least four months in advance of making the alteration, communicate particulars of the change to Pakistan in writing and the provisions of Paragraphs 10 and 11 shall then apply, but the period of three months specified in Paragraph 10 shall be reduced to two months.
  1. where a Plant is located at a site on the Chenab Main below Ramban, the volume of water received in the river upstream of the Plant in any one period of 24 hours shall be delivered into the river below the Plant within the same period of 24 hours;
  2. where, a plant is located at a site on the Chenab Main above Ramban, the volume of water delivered into the river below the Plant in anv one period of 24 hours shall not be less than 50% and not more than 130%, of the volume received above the Plant during the same 24-hour period; and
  3. where a Plant is located on a Tributary of The Jhelum on which Pakistan has any Agricultural Use or hydro-electric use, the water released below the Plant may be delivered, if necessary, into another Tributary but only to the extent that the then existing Agricultural Use or hydro-electric use by Pakistan on the former Tributary would not be adversely affected.
  1. a tolerance of 10% in volume shall be permissible; and
  2. Surcharge Storage shall be ignored.
  1. the aggregate designed maximum discharge through the turbines does not exceed 300 cusecs;
  2. no storage is involved in connection with the Small Plant, except, the Pondage and the storage incidental to the diversion structure; and
  3. the crest of the diversion structure across the Tributary, or the top level of the gates, if any, shall not be higher than 20 feet above the mean bed of the Tributary at the site of the structure.
  1. the work-, incorporate no storage other than Pondage and I the Dead Storage incidental to the diversion structure, and
  2. no additional supplies are run in the irrigation channel for the purpose of generating hydro-electric power.

APPENDIX I To ANNEXURE D (Paragraph 5)

Probable date of completion of river works, and dates on which various stages of the plant would come into operation.

APPENDIX H To ANNEXURE D (Paragraph 9)

(a) period as available; estimated data will be given for as long

(b)period as possible; in both cases data may be limited to the latest 25 years).

(c) Flood data, observed or estimated (with details of estimation).

(d) Gauge-discharge curve or curves for site or sites mentioned in (a) above.

  1. Stage-area and stage-capacity curves of the reservoir, forebay and Regulating Basin, with contoured survey maps on which based.
  2. Full Pondage Level, Dead Storage Level and Operating Pool together with the calculations for the Operating Pool.
  3. Dead Storage capacity.
  4. Estimated evaporation losses in the reservoir, Regulating Basin, head-race, forebay and tall-race.
  5. Maximum designed flood discharge, discharge-capacity curve for spillway and maximum designed flood level.
  6. Designated range of operation.
  1. Dimensioned plan showing dam, spillway, intake and outlet works, diversion works, head-race and forebay, powerhouse, tail-race and Regulating Basin.
  2. Type of dam, length and height above mean bed of river.
  3. Cross-section of the river at the site; mean bed level.
  4. Type of spillway, length and crest level; size, number and top level of spillway gates.
  5. Type of intake, maximum designed capacity, number and size, sill levels; diversion works.
  6. Head-race and tail-race : length, size, maximum-, designed capacity.

Probable date of completion of river works, and dates on which various stages of the plant would come into operation.

APPENDIX III To ANNEXURE D (Paragraph 19)

(a) period as available; estimated data will be given for as long

(b)period as possible; in both cases data may be limited to the latest 25 years).

(c) Flood data, observed or estimated (with details of estimation).

(d) Gauge-discharge curve or curves for site or sites mentioned in (a) above.

  1. Stage-area and stage-capacity curves of the reservoir, forebay and Regulating Basin, with contoured survey maps on which based.
  2. Full Pondage Level, Dead Storage Level and Operating Pool together with the calculations for the Operating Pool.
  3. Dead Storage capacity.
  4. Estimated evaporation losses in the reservoir, Regulating Basin, head-race, forebay and tall-race.
  5. Maximum designed flood discharge, discharge-capacity curve for spillway and maximum designed flood level.
  6. Designated range of operation.
  1. Dimensioned plan showing dam, spillway, intake and outlet works, diversion works, head-race and forebay, powerhouse, tail-race and Regulating Basin.
  2. Type of dam, length and height above mean bed of river.
  3. Cross-section of the river at the site; mean bed level.
  4. Type of spillway, length and crest level; size, number and top level of spillway gates.
  5. Type of intake, maximum designed capacity, number and size, sill levels; diversion works.
  6. Head-race and tail-race : length, size, maximum-, designed capacity.
  7. Outlet works: function, type, size, number, maximum designed capacity and sill levels.
  8. Discharge proposed to be passed through the Plant, initially and ultimately, and expected variations in the discharge on account of the daily and the weekly load fluctuations.

(i) Maximum aggregate capacity of power units (exclusive of standby units) for Firm Power and Secondary Power.

(ii) Regulating Basin and its outlet works : type, number, size, sill levels and designed maximum discharge capacity.

  1. Estimated effect of proposed development on the flow pattern below the last plant downstream (with details of estimation),.
  2. Probable date of completion of river works, and dates on which various stages of the Plant would come into operation.

APPENDIX III To ANNEXURE D (Paragraph 19)

ANNEXURE E-STORAGE OF WATERS BY INDIA ON THE WESTERN RIVERS (Article III (4))

(i) Maximum aggregate capacity of power units (exclusive of standby units) for Firm Power and Secondary Power.

(ii) Regulating Basin and its outlet works : type, number, size, sill levels and designed maximum discharge capacity.

  1. Estimated effect of proposed development on the flow pattern below the last plant downstream (with details of estimation),.
  2. Probable date of completion of river works, and dates on which various stages of the Plant would come into operation.

APPENDIX III To ANNEWRE D (Paragraph 19)

ANNEXURE E-STORAGE OF WATERS BY INDIA ON THE WESTERN RIVERS (Article III (4))

(1)' "Multi-purpose Reservoir" means a reservoir capable of and intended for use for more than one purpose.

(in) "Single-purpose Reservoir" means a reservoir capable of and intended for use for only one purpose.

(n) "Small Tank" means a tank having a Live Storage of less than 700 acre-feet and fed only from a non-perennial small stream : Provided that the Dead Storage does not exceed 50 acre-feet.

  1. If any alteration proposed in the design of any of the Storage Works referred to in Paragraph 3 would result in a material change in the information furnished to Pakistan under the provisions of Paragaph 4, India shall, at least 4 months in advance of making the alteration, communicate particulars of the change to Pakistan in writing and the provisions of Paragraph 6 shall then apply.
  2. In the event of ' an emergency arising which requires repairs to be undertaken to protect the integrity of any of the Storage Works referred to in Paragraph 3, India may undertake immediately the necessary repairs or alterations and, if these repairs or alterations result in a change in the information furnished to Pakistan under the provisions of Paragraph 4, India shall as soon as possible communicate particulars of the change to Pakistan in writing. The provisions of Paragraph 6 shall then apply.
  1. the storage specified in Column (3) above may be used for any purpose whatever, including the generation of electric energy;
  2. the storage specified in Column (4) above may also be put to Non-Consumptive Use (other than flood protection or flood control) or to Domestic use;
  3. India shall have the option. to increase the Power Storage Capacity specified against item (d) above by making a reduction by an equal amount in the Power Storage Capacity specified against items (b) or (e) above; and
  4. Storage Works to provide the Power Storage Capacity on the Chenab main specified against item (e) above shall not be constructed at a point below Naunut (Latitude 33' 19' N. and Longitude 75' 59' E.)
  1. Storage in any Small Tank.
  2. Any natural storage in a Connecting Lake, that is to say, storage not resulting from any man-made works.
  3. Waters which, without any man-made channel or works, spill into natural depressions or borrow-pits during floods.
  4. Dead Storage.
  5. The volume of Pondage for hydro-electric plants under Annexure D and under Paragraph 21 (a).
  6. Surcharze Storaae.
  7. Storage in a Regulating Basin (as defined in Annexure D.)
  8. Storage incidental to a barrage on the Jhelum Main or on the Chenab Main not exceeding 10,000 acre-feet.
  1. any storage which may be effected by such works shall be confined to off-channel storage in side valleys, depressions or lakes and will not involve any storage in the Jhelum Main itself; and
  2. except for the part held in lakes, borrow-pits or natural depressions, the stored waters shall be released as quickly as possible after the flood recedes and returned to the Jhelum Main lower down.

These works shall be constructed in accordance with the provisions of Paragraph 11(d).

  1. The Storage Work shall not be capable of raising artificially the water level in the reservoir higher than the designed Full Reservoir Level except to the extent necessary for Flood Storage, if any, specified in the design.
  2. The design of the works shall take due account of the requirements of Surcharge Storage.
  3. The volume between the Full Reservoir Level and the Dead Storage Level of any reservoir shall not exceed the Conservation Storage Capacity specified in the design.
  4. With respect to the Flood Storage mentioned in Paragraph 9, the design of the works on the Jhelum Main shall be such that no water can spill from the Jhelum Main into the off-channel storage except when the water level in the Jhelum Main rises above the low flood stage.
  5. Outlets or other works of sufficient capacity shall be provided to deliver into the river downstream the flow of the river received upstream of the Storage Work, except during freshets or floods. These outlets or works shall be located at the highest level consistent with sound and economical design and with satisfactory operation of the Storage Work.
  6. Any outlets below the Dead Storage Level necessary for sediment control or any other technical purpose shall be of the minimum size, and located at the highest level, consistent with sound and economical design and with satisfactory operation of the Storage Work.
  7. If a power plant is incorporated in the Storage Work, the intakes for the turbines shall be located at the highest level consistent with satisfactory and economical construction and operation of the plant and withk customary and accepted practice of design for the designated range of the plant's operation.
  8. To enable Pakistan to satisfy itself that the design of a Storage Work (other than a Storage Work falling under Paragraph 3) conforms to the criteria mentioned in Paragraph 11, India shall, at least six months in advance of the beginning of construction of the Storage Work, communicate to Pakistan in writing the information specified in the Appendix to this Annexure; if any such information is not available or is not pertinent to the design of the Storage Work or to the conditions at the site, it will be so stated :

Provided that, in the case of a Storage Work falling under Paragraph 9,

(i) if the work is a new work, the period of six months shall be reduced to four months, and

(ii) if the work is a work under construction on the Effective Date, the information shall be furnished not later than 31st December, 1960.

  1. If any alteration proposed in the design of a Storage Work (other than a Storage Work failing under Paragraph 3) before it comes into operation would result in a material change in the information furnished to Pakistan under the provisions of Paragraph 12, India shall immediately communicate particulars of the change to Pakistan in writing and the provisions of Paragraphs 13 and 14 shall then apply, but where a period of three months is specified in Paragraph 13, that period shall be reduced to two months.
  2. If any alteration proposed in the design of a Storage Work (other than a Storage Work falling under Paragraph 3), after it comes into operation would result in a material change in the information furnished to Pakistan under the provisions of Paragraph 12, India shall, at least four months in advance of making the alteration, communicate particulars of the change to Pakistan in writing and the provisions of Paragraph 13 and 14 shall then apply, but where a period of three months is specified in Paragraph 13, that period shall be reduced to two months.
  1. if the site is on The Indus, between 1st June and 20th August;
  2. if the site is on The Jhelum, between 21st June and 20th August; and
  3. if the site is on The Chenab, between 21st June and 31st August at such rate as not to reduce, on account of this filling, the flow in the Chenab Main above Merala to less than 55,000 cusecs.
  1. the maximum Pondage (as defined in Annexure D) shall not exceed the Pondage required for the firm power of the plant, and the water-level in the reservoir corresponding to maximum Pondage shall not, on account -of this Pondage, exceed the Full Reservoir Level at any time; and
  2. except during the period in which a filling is being carried out in accordance with the provisions of Paragraph 18 or 19, the volume of water delivered into the river below the work during any periodof seven consecutive days shall not be less than the volume of water received in the river upstream of the work in that seven-day period.
  1. the period of seven consecutive days shall commence at 8 A.M. on every Saturday and the time shall be Indian Standard Time;
  2. a tolerance of 10% in volume shall be permissible and adjusted as soon as possible; and (c) any temporary uncontrollable retention of water due to variation in river supply will be accounted for.

APPENDIX To ANNEXURE E

(Paragraphs 4 and 12)

(1) Stage-area and stage-capacity curves of forebay and Regulating Basin, with contoured survey maps on which based.

(ii) Estimated evaporation losses in the Regulating Basin, head-race, forebay and tail-race.

(iii) Designated range of operation.

  1. Dimensioned plan showing dam, spillway, diversion works and outlet works.
  2. Type of dam, length and height above mean bed of the river.
  3. Cross-section of the river at the site and mean bed level.
  4. Type of spillway, length and crest level; size, number and top level of spillway gates.
  5. Type of diversion works, maximum designed capacity, number and size; sill levels.
  6. Outlet works : function, type, size, number, maximum designed capacity and sill levels.
  7. If a power plant is incorporated in a Storage Work,
  1. Dimensioned plan showing head-race and forebay, powerhouse, tail-race and Regulating Basin.
  2. Type of intake, maximum designed capacity, size and sill level.
  3. Head-race and tail-race, length, size and maximum designed capacity.
  4. Discharge proposed to be passed through the plant, initially and ultimately, and expected variations in the discharge on account of the daily and the weekly load fluctuations.
  5. Maximum aggregate capacity of power units (exclusive of standby units) for firm power and secondary power.
  6. Regulating Basin and its outlet works : type, number, size, sill levels and designed maximum discharge capacity.
  1. Probable date of completion of river works and probable dates on which various stages of the work would come into operation.
  2. Estimated effect of proposed Storage Work on the flow pattern of river supplies below the Storage Work or, if India has any other Storage Work or Run-of-River Plant (as defined in Annexure D) below the proposed Storage Work, then on the flow pattern below the last Storage Work or Plant.

ANNEXURE F-NEUTRAL EXPERT (Article IX (2))

Part l-Questions to be referred to a Neutral Expert

ANNEXURE G-Court OF ARBITRATION (Article IX (5))

(a) International conventions establishing rules which are expressly recognized by the Parties.

(b) Customary international law.

Part 2-Distribution of the Water of The Ravi

Part 3-Distribution of the Water of The Sutlej and The Beas in Kharif during Phase I

Part 4-Distribution of the water of The Sutlej and The Beas in Kharif during Phase II

Part 5-Distribution of the waters of The Sutlej and The Beas in Rabi

Part 6-Water-accounts at Ferozepore

Part 7-Financial provisions

Part 8-Extension of Transition Period

Part 10--Special provisions for 1960 and 1961

Appendix I- Provisions for Time-lag and for Determination of the 'Sutlej Component at Ferozepore' and the Seas Component at Ferozepore'

Appendix II--Forms of water-account

Appendix III-Calculations for determining proportionate working expenses to be paid by Pakistan under the provisions of Paragraph 48 and 50

Appendix IV-Calculations for determining proportionate working expenses to be paid by Pakistan under the provisions of Paragraphs 49 and 50

In framing, operating and, if necessary, modifying the rotational programme, the Chief Engineer, Punjab, will make every effort to see that, within each of the Water-accounting Periods specified above, the supplies delivered to the C.B.D.C. are spread out over the period as fairly as the prevailing circumstances permit.

  1. any discharge observation made by India whenever it may consider necessary to do so, but not more often than once in two months; or
  2. any joint discharge observation by India and Pakistan which may be undertaken at the request of either Commissioner, but not more often than once in three months; the observation shall be made within a fortnight of the receipt of the request.

India will supply to Pakistan, for each channel specified in Table A, a copy of the discharge table current on the Effective Date and of any revised discharge table prepared thereafter in accordance with (i) or (ii) above.

  1. The supply available from the 'Sutlej Component at Ferozepore' and from the 'Beas Component at Ferozepore' less the withdrawals due to be made by India under the provisions of Paragraphs 21 (b), 22 and 23.
  2. The appropriate 'gross amount', as at Ferozepore, detormined in accordance with Paragraph 22 (b).

(i) the supplies required at Trimmu above to meet the withdrawals of the Haveli and Panjnad Canals (after allowing a time-lag of five days from Trimmu to Panjnad), and

(ii) 7,500 cusecs during Phase I or 10,000 cusecs during Phase II, the deliveries specified in Paragraph 34(e) may be reduced, during March 1-10, 11-20 and 21-31 in that year, by amounts related to Pakistan's ability to replace. For March 1-10, 11-20 and 21-31, these amounts shall be taken as equal to 60 per cent of the 'gross amount' determined as follows :

When the sum of (a) the average discharge at Merala Above (obtained by limiting the daily values to a maximum of 25,000 cusecs during March 1-10, a maximum of 26,000 cusecs during March 11-20 and a maximum of 27,000 cusecs during March 21-31) and (b) the Ravi Component at Balloki Above (total supply at Balloki. Above minus the delivery at U.C.C. tall minus the delivery at M.R. Link outfall minus the delivery into the Ravi Main through B.R.B.D. escapes, the result being limited to a minimum of zero) is less than or equal to the Floor Discharge shown in Column (2) of Table C below, the 'gross amount', as at Ferozepore, shall be zero. When this sum equals or exceeds the Ceiling Discharge shown in Column (3) of Table C, the 'gross amount', as at Ferozepore, shall be the amount shown in Column (4) of Table C. When the sum is between the values shown in the said Columns (2) and (3), the 'gross amount', as at Ferozepore, shall be the proportional intermediate amount.